work performance information is circulated through(  ) processes.
A、 planning
B、 change
C、 improvement
D、 communication


相關試題

72題: () seek to perform root cause investigation as to what is leading identified trends.
A、 incident management
B、 prob lem management
C、change management
D、know ledge management
答案解析與討論:www.dalwkz.tw/st/4138916043.html

73題: the (  ) is a graph that shows the relationship between two variables.
A、histograms
B、flowcharts
C、matrix diagrams
D、Scatter diagrams
答案解析與討論:www.dalwkz.tw/st/4139014581.html

74題: (  )is the process of identifying individual project risks as well as source of overall project risk, and documenting their characteristics.
A、identify risks
B、monitor risks
C、impIement risks responses
D、plan risk management